Tentative Schedule
Exit 1
6/1 – 6/4 SB exit ramp
7am-6pm Partial Ramp Closure (1/2 ramp closed, traffic shifted and channelized through ramp
6pm-7am Ramp completely closed to traffic
6/1 – 6/8 SB entrance ramp
7am-6pm Partial Ramp Closure (1/2 ramp closed, traffic shifted and channelized through ramp)
6pm-7am Ramp completely closed to traffic
6/8 – 6/12 NB exit ramp
7am-6pm Partial Ramp Closure (1/2 ramp closed, traffic shifted and channelized through ramp)
6pm-7am Ramp completely closed to traffic
6/9 – 6/16 NB entrance ramp
7am-6pm Partial Ramp Closure (1/2 ramp closed, traffic shifted and channelized through ramp)6pm-7am Ramp completely closed to traffic
7/6-7/10 Stripe all ramps
6pm-7am Ramp completely closed to traffic
Exit 3 (Loop Ramps only)
9/9-9/16 SB entrance ramp Closed 7 consecutive days to traffic, with detour
9/19-9/26 NB exit ramp Closed 7 consecutive days to traffic, with detour